NYCSCA – Boiler Conversion & Climate Control Upgrade at IS 145Q
Project Location
Queens, NY
Scope of Services
Demolition
Installation of new boiler plant and associated equipment
Project Construction Cost
$8,215,985
Key Dates:
January 2017 – March 2019
Job Description
Maric Mechanical Inc. was first tasked with the demolition and removal of the existing boiler plant and associated equipment. Following this, a single 350hp mobile steam boiler was utilized to provide temporary heat to the occupied school while work commenced on the installation of the new boiler plant. Irregular hours were worked to help facilitate minimal disturbance to daily school activity so classes were able to proceed as normal due to proper coordination of work in populated areas.