NYCHHC- Lincoln Medical Center
Project Location
Bronx, NY
Scope of Services
Demolition
Installation of new cooling tower
Project Construction Cost
$8,797,706
Key Dates
October 2017 - October 2018
Job Description
Maric Mechanical. Inc was first required to perform the demolition and removal of the existing Marley cooling tower and associated piping on top of the hospital’s service building. Five new Delta cooling towers with VFD, vibration sensors, interconnecting catwalks, and associated piping were then installed. Modifications, repairs, and select replacement of existing steel dunnage and electrical systems to accommodate the new towers and associated equipment, including wiring, switches, and new switchgear.